RAJUK Plan Approval Checklist
Complete process guide for Planning Permit (LUC), Construction Permit, Special Project Approval, Occupancy Certificate, Fire NOC, and departmental clearances.
Produced by PlanBD · Bangladesh Development Intelligence Platform · June 2026
🏛1. Overview & Legal Framework
Any building construction within RAJUK's jurisdiction (1,528 sq km of Dhaka Metropolitan Area) legally requires prior approval. Without it, you face demolition orders, heavy penalties, and cannot obtain an Occupancy Certificate.
| Building Act | Building Construction Act, 1952 (Act No 1107 of 1953) |
|---|---|
| Primary Rules | Dhaka Imarat Nirman Bidhimala 2025 (latest, replaces 2008 rules) |
| Area Plan | Detailed Area Plan (DAP) 2022–2035 – governs FAR, zoning, density |
| Building Code | Bangladesh National Building Code (BNBC) 2020 – structural, fire, safety |
| Online System | ECPS – Electronic Construction Permitting System (launched 2024) |
| Portal | ecps.gov.bd (previously cp.rajuk.gov.bd) |
| Regulator | RAJUK – Rajdhani Unnayan Kartripakkha |
The Two-Stage Mandatory Process
| Stage | Name | Form | Validity | Fee |
|---|---|---|---|---|
| 1 | Planning Permit (LUC) | Form-101 | 24 months (+ 12 renewal) | Tk 5,000 + 15% VAT |
| 2 | Construction Permit | Form-301 | 3 years (to plinth level) | Variable (see p.8) |
| 3* | Special Project Approval | Form-201 | 24 months (non-renewable) | Tk 10,000 + 15% VAT |
| 4* | Occupancy Certificate | — | 5 years (renewable) | Variable |
* Stage 3 required for large/special projects. Stage 4 required after construction completion.
📍2. PHASE 1 – Planning Permit (LUC) | Form-101
The Planning Permit (formerly Land Use Clearance / LUC) is the mandatory first step. It is submitted online through ECPS to RAJUK's Town Planning Department. All documents must be uploaded as original-color JPEG or PNG scans.
2a. Documents Checklist – All Plot Types
| Document / Item | Notes | Status |
|---|---|---|
Land Registry (deed of land) | Original color scan, JPEG/PNG | Required |
Mutation Certificate | Must be up to date | Required |
National ID (NID) or Passport | Owner or authorized representative | Required |
CS, RS and MS Khatian | All three khatians required | Required |
Duplicate Carbon Receipt (DCR) | From relevant sub-registry office | Required |
Updated Land Tax Receipt | Current year's tax clearance | Required |
TIN Certificate | Income Tax Identification Number | Required |
TAX Return Acknowledgement Slip | Latest year's tax return | Required |
Passport-size Photo | 1 copy of landowner | Required |
LUC Application Form-101 | Filled and digitally signed online via ECPS | Required |
Application Fee Payment Proof | Bank draft in favor of RAJUK + 15% VAT | Required |
Additional Documents – Private / NHA Housing Land
| Document / Item | Notes | Status |
|---|---|---|
Possession Letter | Issued by housing authority | If applicable |
Provisional and Final Allotment Letter | — | If applicable |
Layout Plan from Housing Office | — | If applicable |
Payment Clearance Slip | — | If applicable |
Sale Permission | If plot was transferred | If applicable |
Re-construction Permission | If replacing existing structure | If applicable |
Lease Deed with Housing Company | — | If applicable |
Mutation Permission from Housing Authority | — | If applicable |
Time Extension Letter | If allotment has been extended | If applicable |
Additional Documents – RAJUK Plots (Uttara, Purbachal, Jheelmil, Banani, Gulshan, Baridhara)
| Document / Item | Notes | Status |
|---|---|---|
MIS Clearance from RAJUK | From RAJUK's MIS department | Required |
Field Survey Report by RAJUK Surveyor | Must be conducted by authorized RAJUK surveyor | Required |
Transfer Declaration Letter | If plot was transferred to current owner | If applicable |
Drawings Required for LUC Submission
| Document / Item | Notes | Status |
|---|---|---|
Digital Land Survey Report | Scale 1:5,000 or 1:10,000 | Required |
Site Plan showing land use within 250m radius | Size: 15cm × 20cm | Required |
Location Map of Land | Showing plot in context of area | Required |
Width of Nearest Road (marked on plan) | — | Required |
RS, CS Map Pantograph Drawing | Official map tracing | Required |
Information to Fill in Form-101 (Online)
- Name of applicant / landowner
- Present address of applicant
- Proposed land location (CS/RS Dag No, Mouza, Thana)
- Area of land in Katha
- Existing land use of plot
- Proposed land use
- Name and width of connecting road
- Elevation of land with respect to road (Reduced Level)
- Land use of surrounding plots (North, South, East, West)
- Ownership history of plot
- Other land information (if any)
2b. Fees, Timeline & Validity
| Application Fee | Tk 5,000 + 15% VAT (per draft 2025 rules) Bank draft payable to RAJUK at a scheduled bank |
|---|---|
| Processing Time | Official: 30 days from submission (May vary in practice) |
| Validity | 24 months from date of approval |
| Renewal | Additional 12 months via Form-111 (before expiry) |
| Expired LUC | Must re-apply from scratch – previous LUC cannot be reactivated |
🏗3. PHASE 2 – Construction Permit | Form-301
After obtaining a valid Planning Permit, apply for the Construction Permit through ECPS using Form-301. This must be submitted within the 24-month LUC validity period. Five drawing sets must be submitted digitally on Ammonia-printed sheets (A0–A2).
3a. Documents Checklist
| Document / Item | Notes | Status |
|---|---|---|
Online Application (Form-301) | Submitted via ecps.gov.bd | Required |
Valid Planning Permit / LUC Copy | Must be within 24-month validity | Required |
Bank Draft – Building Approval Fee | Payable to RAJUK + 15% VAT | Required |
All Land Documents (as in LUC section) | Same set as Phase 1 | Required |
Soil Test Report | Required for buildings on weak soil; check with RAJUK | If applicable |
FAR Calculation Sheet | Showing MGC, setbacks, number of storeys, FAR | Required |
Ammonia-printed Approval Drawing Sheets (A0–A2) | 5 drawing sets – see Section 3b | Required |
Indemnity Bond for Piling / Basement Construction | If piling or basement is proposed | If applicable |
Floor-wise Number of Apartments | For residential buildings | Required |
RAJUK Registration Certificate – Design Architect | With IAB membership number | Required |
RAJUK Enlistment Certificate – Structural Engineer | With IEB membership number | Required |
RAJUK Enlistment Certificate – Electrical Engineer | With IEB membership number | Required |
RAJUK Enlistment Certificate – Plumbing Engineer | With IEB membership number | Required |
Fire Expert Certification | Required if Fire Design is submitted | If applicable |
Land Surrender Deed to DNCC/DSCC | If road expansion affects the plot boundary | If applicable |
3b. Required Drawing Sets (5 sets – all Ammonia printed A0–A2)
① Architectural Design (signed by RAJUK-registered Architect)
| Document / Item | Notes | Status |
|---|---|---|
Title block with applicant name, address, mobile, signature | — | Required |
Architect's name, IAB membership no., RAJUK registration no., signature | — | Required |
Structural engineer's details on architectural sheet | — | Required |
LUC approval reference number and date | — | Required |
Occupancy type of proposed building | — | Required |
CS/RS/SA Dag No., Mouza, Thana name | — | Required |
Site Plan (Scale 1:4,000) with boundaries, road width, entry position | — | Required |
Layout Plan (Scale 1:200) – boundary, existing buildings, sewer/water connections | — | Required |
All Floor Plans (Scale 1:100) – room dimensions, door/window sizes, parking | — | Required |
Roof Plan – terrace, chilakatha, lift machine room, OHWT, water disposal | — | Required |
Two Cross-Sections (Scale 1:100) – floor heights, lift, stairs, plinth level | — | Required |
Four Elevations (N/S/E/W) Scale 1:100 | — | Required |
Waste collection point location | — | Required |
Generator and sub-station room location | — | Required |
② Structural Design (signed by RAJUK-enlisted Structural Engineer)
| Document / Item | Notes | Status |
|---|---|---|
Foundation design and type | — | Required |
Column-beam-slab layout for all floors | — | Required |
Structural analysis for earthquake, wind, dead & live loads (BNBC 2020) | — | Required |
Piling plan with indemnity bond (if applicable) | — | If applicable |
Engineer's IEB membership and RAJUK enlistment details | — | Required |
③ Plumbing Design (signed by RAJUK-enlisted Plumbing Engineer)
| Document / Item | Notes | Status |
|---|---|---|
Water supply layout (floor-wise) | — | Required |
Drainage and sewage plan | — | Required |
Underground water reservoir (UGWR) capacity and location | — | Required |
Overhead water tank (OHWT) capacity and location | — | Required |
Septic tank design (if not connected to WASA sewer) | — | If applicable |
Soak well / soakpit design | — | If applicable |
④ Electrical Design (signed by RAJUK-enlisted Electrical Engineer)
| Document / Item | Notes | Status |
|---|---|---|
Single-line electrical diagram | — | Required |
Load calculation sheet | — | Required |
Sub-station and generator room location | — | Required |
Lift electrical connections (mandatory >6 floors) | — | If applicable |
Emergency lighting and exit signage plan | — | If applicable |
⑤ Fire Safety Design (signed by certified Fire Expert) — IF REQUIRED
| Document / Item | Notes | Status |
|---|---|---|
Fire exit staircase layout (mandatory >10 storeys or >33m height) | — | If applicable |
Fire lift (dedicated) details | — | If applicable |
Sprinkler system layout (high-rise) | — | If applicable |
Hydrant / hose reel system layout | — | If applicable |
Smoke detector / fire alarm layout | — | If applicable |
Fire-rated door and wall locations | — | If applicable |
Water tank dedicated for fire use | — | If applicable |
3c. Professional Qualifications Required
| Role | Qualification | Membership | Experience |
|---|---|---|---|
| Design Architect | B.Arch from IAB-accredited university | Member of IAB | Min 8 years; RAJUK registered under DAP 2022-2035 |
| Structural Engineer | BSc Civil Engineering from IEB-accredited university | Member/Fellow of IEB | Min 8 years civil; 5 years structural; RAJUK enlisted (SEng/PEng) |
| Electrical Engineer | BSc Electrical Engineering | Member of IEB | RAJUK enlisted |
| Plumbing Engineer | BSc Civil / Mechanical Engineering | IEB membership | RAJUK enlisted |
| Fire Expert | Certified fire safety specialist | FSCD recognized | Required for fire-design submission |
3d. Fees, Timeline & Validity
Fees are calculated per floor area. The table below shows the current fee schedule (subject to revision under draft Bidhimala 2025):
| Building Type / Floor Area | Approval Fee (approx.) | Notes |
|---|---|---|
| Residential – small plot, low rise | Tk 10,000 – 50,000 | + 15% VAT |
| Residential – 5,000 sqm | Tk 42,500 (current) → Tk 250,000 (proposed) | Draft 2025 |
| Large residential / commercial – 30,000 sqm | Significantly higher | Draft 2025 |
| Multi-unit block – per katha surcharge | Tk 5,000/katha (proposed) | Draft 2025 |
| Processing Time | Official processing: variable; RAJUK targets ~45 days via ECPS |
|---|---|
| Plan Validity | 3 years from approval date |
| Construction Requirement | Must reach plinth level within validity period |
| Failure to Build to Plinth | Approved plan becomes invalid – must re-apply |
| Re-approval Penalty | 10× the original approval fee + committee-set compensation |
Special Conditions
- ⚠ Plot must be completely vacant before plan submission
- ⚠ Boundary wall must be broken / land surrendered for any proposed road expansion
- ⚠ Minimum proposed road width: 20 ft (public land) / 25 ft (housing land) / 12 ft (shared)
- ⚠ Minimum plot entry gate width: 18 feet
- ⚠ Driveway must be minimum 14 feet wide
- ⚠ Lift is mandatory for buildings more than 6 (six) storeys
- ⚠ Fire stairs mandatory for buildings >33m in height or >10 storeys (whichever comes first)
- ⚠ CAAB height clearance required if plot is near airport or runway
🏢4. PHASE 3 – Special / Large Project Approval | Form-201
Certain projects are classified as 'Special Projects' under Dhaka Mahanagar Imarat Nirman Bidhimala 2025 and require additional approval from RAJUK's Special Project Approval Committee before the construction permit can be issued.
Projects That Qualify as Special Projects
| Document / Item | Notes | Status |
|---|---|---|
Residential building with more than 40 flats | — | Required |
Gross Floor Area exceeds 7,500 sqm (per FAR) | — | Required |
Shopping mall with more than 5,000 sqm floor area | — | Required |
Project connecting to a National or Regional Highway | — | Required |
Brick field or hazardous industrial factory | — | Required |
Any project within 250m of a Historical/Heritage Building | — | Required |
Any project within 250m of parks or natural beauty areas | — | Required |
Project within 50m of a hilly area or river bank | — | Required |
Any project within 250m of KPI (Key Point Installation) | — | Required |
Documents Required for Special Project Application
| Document / Item | Notes | Status |
|---|---|---|
Land use clearance copy / No-objection copy | — | Required |
Ownership evidence / Land Registry copy | — | Required |
CS, RS, MS Map | — | Required |
Dag No., Mouza and Thana Name | — | Required |
Khatian, Mutation documents | — | Required |
Number of storeys in proposed building | — | Required |
Total cumulative floor area (GFA) | — | Required |
Floor-wise area mentioning use type | — | Required |
Total number of flats (for residential) | — | Required |
FAR Calculation Chart | — | Required |
Required water demand of proposed project | — | Required |
Source of water and supply network diagram | — | Required |
Required electricity load for project | — | Required |
Source of electricity and single-line diagram | — | Required |
Construction start date and phasing plan | — | Required |
Estimated construction completion duration | — | Required |
Special Project Approval Drawings Must Include
| Document / Item | Notes | Status |
|---|---|---|
Key plan with site boundary measurements | — | Required |
North directional sign of proposed site | — | Required |
Name and width of connecting road | — | Required |
Holding No., Plot No., and Mouza name | — | Required |
Plot elevation relative to road level | — | Required |
Information on existing buildings inside project boundary | — | Required |
Adjacent building height and distance from plot boundary | — | Required |
Vehicle and pedestrian entry/exit | — | Required |
Drainage system and disposal network | — | Required |
Location of electrical sub-station | — | Required |
Wastewater and sewerage treatment plant (STP) detail | — | Required |
Garbage collection and disposal management plan | — | Required |
Any special building or facility within 250m of proposed land | — | Required |
| Processing Time | Official: 45 days from application submission |
|---|---|
| Application Fee | Tk 10,000 + 15% VAT (bank draft to RAJUK) |
| Validity | 24 months from approval date |
| Renewable? | NO – Special Project approval cannot be renewed |
| Failure to Apply for CP | Must re-apply for Special Project approval from scratch |
⚡5. Departmental Clearances (>10 Storeys / >33m)
Buildings more than 10 storeys or above 33 metres in height require departmental clearances from 10 separate authorities before RAJUK will issue the Construction Permit. Apply to each in plain paper with location details and related drawings.
| # | Authority | Purpose | Notes |
|---|---|---|---|
| 1 | DPDC / DESCO / BREB (Power Division) | Electrical load requirement clearance | State electricity demand and sub-station details |
| 2 | DWASA (Water & Sewage Authority) | Water consumption and sewerage clearance | Submit water demand calculation |
| 3 | Titas Gas & Transmission Authority | Gas connection requirement | Submit gas load calculations |
| 4 | FSCD (Fire Service & Civil Defence) | Fire Safety NOC | Mandatory for >6 storeys (see Section 6) |
| 5 | DoE (Dept. of Environment) | Environmental clearance / ECC | May require EIA for large projects (see Section 7) |
| 6 | CAAB (Civil Aviation Authority) | Height clearance near airports | Required near Hazrat Shahjalal International Airport runway corridors |
| 7 | Roads & Highways / City Corporation | Road connection / access approval | If project connects to major road |
| 8 | Telecom Authority (BTRC) | Telecom infrastructure clearance | For large commercial buildings |
| 9 | District Commissioner / Deputy Commissioner | Land-related NOC | If land has any government acquisition status |
| 10 | Department of Explosives / Petroleum Corp. | Hazardous use clearance | For industrial/chemical uses only |
🔥6. Fire Safety NOC Requirements
The Fire Service & Civil Defence (FSCD) is the enforcing body for fire-safety compliance and NOCs in Bangladesh. Requirements scale by building height, type, and occupancy. Fire NOC must be obtained from FSCD before RAJUK issues the construction permit for qualifying buildings.
Fire NOC Trigger Thresholds
| Document / Item | Notes | Status |
|---|---|---|
Building >6 storeys (high-rise threshold) | Full fire safety system required | Required |
Building >10 storeys or >33m height | Fire stairs + fire lift mandatory | Required |
Commercial building / shopping mall | Stricter requirements based on occupant load | Required |
Assembly occupancy (school, hospital, cinema) | Highest fire safety standards | Required |
Industrial / factory / warehouse | Fire licence from FSCD required | Required |
Restaurant or food court (any floor) | Especially if above ground floor | Required |
Fire Safety Requirements by Category
| Requirement | Applicable To | Standard |
|---|---|---|
| Fire Exit Staircase | >10 storeys or >33m | BNBC 2020 / FSCD norms |
| Dedicated Fire Lift | >10 storeys or >33m | Separate from passenger lifts |
| Sprinkler System | High-rise, malls, assembly | Full floor coverage |
| Fire Hydrant / Hose Reels | >6 storeys; commercial | Every floor, accessible |
| Smoke Detectors / Fire Alarm | >6 storeys | All floors, all rooms |
| Fire-rated Doors & Walls | Exit corridors & stairwells | Minimum 2-hour rating |
| Dedicated Water Tank (fire use) | >10 storeys; commercial | Minimum capacity per FSCD |
| Emergency Lighting & Exit Signs | >6 storeys; assembly | All exits, stairwells |
| Portable Fire Extinguishers | All buildings | Placed per BNBC schedule |
| Assembly Point / Refuge Area | >10 storeys; assembly | Designated & marked |
🌱7. Environmental Clearance | DoE / ECC
The Department of Environment (DoE) issues Environmental Clearance Certificates (ECC). Large real estate projects may require a full Environmental Impact Assessment (EIA). Over 8,000 ECCs were issued in 2024, a 22% increase from 2023.
| Document / Item | Notes | Status |
|---|---|---|
Plot size greater than 10 Katha | May require environmental clearance | If applicable |
Project with significant environmental impact | EIA may be required | If applicable |
Project in flood-prone zone | Flood zone clearance required | If applicable |
Project near wetland or water body | Wetland restriction / special clearance | If applicable |
Industrial or factory use | Full EIA mandatory | Required |
Project with heavy waste / effluent discharge | STP / ETP mandatory | If applicable |
Tree removal required for construction | Tree compensation plan required | If applicable |
High noise-generating activities | Noise study may be required | If applicable |
Note: Dhaka Imarat Nirman Bidhimala 2025 mandates Sewage Treatment Plants (STP) for larger buildings. Confirm STP requirements with RAJUK/DoE for your project size.
🏠8. Occupancy Certificate
After construction is complete, an Occupancy Certificate (OC) must be obtained from RAJUK before the building can legally be occupied or used. This is mandatory and cannot be skipped.
| Document / Item | Notes | Status |
|---|---|---|
Construction Completion Report | Certified by architect and structural engineer | Required |
As-Built Architectural Design | Showing actual as-constructed drawings | Required |
As-Built Structural Design | Final structural drawings | Required |
As-Built Electrical Design | Final electrical drawings | Required |
As-Built Plumbing Design | Final plumbing drawings | Required |
Building Services Plan | All MEP services as installed | Required |
Fire NOC (if applicable) | Updated after construction completion | If applicable |
Utility Connection Certificates | WASA, electricity, gas connections confirmed | If applicable |
| Validity | 5 years from date of issue |
|---|---|
| Renewal | Must be renewed every 5 years |
| Expired OC | Approved plan becomes invalid; re-approval requires 10× fee |
| Consequence of No OC | Building cannot be legally occupied; subject to penalty/demolition |
📐9. Key Rules Reference – FAR, Setbacks, Parking & Height
9a. Floor Area Ratio (FAR) – DAP 2022–2035
FAR = Total Cumulative Floor Area ÷ Total Land Area. DAP 2022–2035 sets FAR values by Ward Number, planning area type, and zoning. Planned areas (RAJUK, govt housing) receive higher FAR than unplanned / spontaneous areas.
| Area / Zone | FAR Range | Notes |
|---|---|---|
| Gulshan, Banani, Baridhara (planned) | Up to 6.0–6.5 | High-density planned zones |
| Uttara (planned) | Up to 5.5–6.0 | TOD bonus near MRT stations |
| Dhanmondi, Lalmatia (semi-planned) | 3.0–5.0 | Varies by ward |
| Unplanned spontaneous areas | 2.5–4.5 | Depends on road width |
| TOD Zones (within 500m of MRT) | Bonus FAR up to +1.0 | If 60% open space in block |
| School / College / University | +0.25 bonus FAR | |
| RAJUK/Govt approved housing plot | +0.5 bonus FAR | |
| Open-for-all playground/park | +0.25 bonus FAR |
Use the PlanBD FAR Calculator or visit RAJUK's ward-wise FAR table for your specific plot. FAR values are indexed by Ward Number and planning area designation.
9b. Height Restrictions by Zone – DAP 2022–2035
| Zone / Area | Max Height (approx.) | Notes |
|---|---|---|
| Kuril, Khilkhet, Nikunja (DNCC) | 6 storeys | DAP restriction |
| Uttara | 7 storeys (general) | Higher in TOD zones |
| Gulshan, Banani, Baridhara | 8 storeys (general) | Higher in TOD zones |
| TOD Zone (near MRT station, 500m) | Higher permitted | Block open-space condition |
| Near airport / runway | CAAB clearance required | Apply through RAJUK to CAAB |
| Fire stairs trigger | >10 storeys or >33m | Whichever comes first |
| Lift mandatory | >6 storeys | Compulsory per rules |
9c. Mandatory Setbacks – General Reference
Setbacks depend on road width, plot size, building height, and zone. The FAR Calculation Sheet must show setbacks for all four sides.
| Road Width (Front) | Min Front Setback | Side Setbacks | Rear Setback |
|---|---|---|---|
| Up to 20 ft | 1.5m – 3m | Per zone rules | Per zone rules |
| 20 – 40 ft | 3m – 4.5m | Per zone rules | Per zone rules |
| >40 ft | 4.5m+ | Per zone rules | Per zone rules |
| High-rise (>10 storeys) | Increased | Increased | Increased |
Precise setback values are defined in the Dhaka Imarat Nirman Bidhimala 2025. Always verify with the FAR calculation sheet from your registered architect.
9d. Parking Requirements – General Reference
Parking requirements are calculated based on building use and gross floor area. The parking plan must show entry, exit, guard post, driveway (min 14 ft wide), disabled bays, visitor bays, and motorcycle bays.
| Building Type | Car Parking | Motorcycle | Notes |
|---|---|---|---|
| Residential apartment | 1 per unit (approx.) | Required | Visitor + disabled bays required |
| Commercial / Office | 1 per 100–150 sqm GFA | Required | Higher in CBDs |
| Shopping mall | 1 per 50–100 sqm GFA | Required | Per BNBC 2020 |
| Hospital | 1 per 3 beds + staff | Required | Ambulance bay required |
| School / College | Per staff + visitor count | Required | Drop-off zone required |
| Disabled parking | Min 2% of total or 2 bays | — | Per BNBC 2020 |
💡10. Common Rejection Reasons & Expert Tips
| Issue | Description | Risk |
|---|---|---|
| Expired LUC | Submitting Construction Permit after the 24-month LUC validity has lapsed | HIGH |
| Incomplete Document Set | Missing any one required document causes full rejection | HIGH |
| Unregistered Professional | Architect or engineer not currently registered with RAJUK | HIGH |
| FAR Exceedance | Proposed GFA exceeds permissible FAR for the ward/zone | HIGH |
| Setback Violation | Building footprint does not respect mandatory setbacks on all sides | HIGH |
| Missing Soil Test | Submitting without soil test when ground conditions require it | MEDIUM |
| Inadequate Parking | Insufficient parking bays relative to floor area | MEDIUM |
| Road Width Non-Compliance | Plot entry gate <18 ft or driveway <14 ft | MEDIUM |
| Incorrect Drawing Scale | Drawings not at specified scales (1:100, 1:200, etc.) | MEDIUM |
| Non-Color Document Scans | Documents scanned in black-and-white instead of original color | MEDIUM |
| JPEG/PNG Format Error | Documents uploaded in incorrect file format | LOW |
| Missing Cross-Sections | Only one section provided instead of two (long + short axis) | LOW |
Expert Tips from Experienced Practitioners
📚11. Regulation Timeline & Amendment History
Understanding the evolution of regulations helps identify which rules apply to your project and whether any recent amendment affects your submission.
| Year | Regulation / Event | Key Impact |
|---|---|---|
| 1952 | Building Construction Act (Act No 1107/1953) | Primary legal authority for all building approvals in Bangladesh |
| 1993 | BNBC – Bangladesh National Building Code (first draft) | First national building code; became legally binding in 2006 |
| 2008 | Dhaka Mahanagar Imarat Nirman Bidhimala 2008 | Primary building rules for Dhaka; governed until 2025 |
| 2010 | RAJUK restructuring | Expanded jurisdiction; introduced systematic plan approval |
| 2020 | BNBC 2020 (updated) | Stricter structural, fire, and environmental standards |
| 2021 | Imarat Nirman Unnayan Poriborton Bidhimala 2021 | Amendment to 2008 rules; introduced new zoning provisions |
| 2022 | DAP 2022–2035 (Detailed Area Plan) | New zoning, FAR limits, height restrictions, TOD zones for Dhaka |
| 2023 | SRO 271/2023 | Amendment to DAP; revised FAR and density rules |
| 2024 | ECPS Launched (ecps.gov.bd) | Full digitization of construction permit process |
| Dec 2025 | DAP Update – 14 December 2025 | Latest update to DAP rules; current benchmark |
| 2025 | Dhaka Imarat Nirman Bidhimala 2025 | NEW – replaces 2008 rules; STP mandates, revised fees, updated FAR |
| 2025–26 | Draft Building Construction Rules 2025 | Proposed fee hikes (5×), new categories; pending gazette notification |
| 2026+ | Future Amendments | Monitor rajuk.gov.bd and ecps.gov.bd for updates |
Official Reference Links
| RAJUK Official | rajuk.gov.bd |
|---|---|
| ECPS Portal (Online Applications) | ecps.gov.bd |
| RAJUK Notices & Circulars | rajuk.gov.bd/pages/notices |
| DAP 2022–2035 Download | Available at rajuk.gov.bd |
| BNBC 2020 Download | Available at hpw.gov.bd |
| Fire Service & Civil Defence | fireservice.gov.bd |
| DoE Environmental Clearance | doe.gov.bd |
| DWASA (Water Authority) | dwasa.org.bd |