RAJUK Plan Approval Checklist

Complete process guide for Planning Permit (LUC), Construction Permit, Special Project Approval, Occupancy Certificate, Fire NOC, and departmental clearances.

Produced by PlanBD · Bangladesh Development Intelligence Platform · June 2026

ECPS Portal
Authority
RAJUK (Rajdhani Unnayan Kartripakkha)
Online Portal
ecps.gov.bd
Key Regulation
DAP 2022–2035
Building Code
BNBC 2020

🏛1. Overview & Legal Framework

Any building construction within RAJUK's jurisdiction (1,528 sq km of Dhaka Metropolitan Area) legally requires prior approval. Without it, you face demolition orders, heavy penalties, and cannot obtain an Occupancy Certificate.

Building ActBuilding Construction Act, 1952 (Act No 1107 of 1953)
Primary RulesDhaka Imarat Nirman Bidhimala 2025 (latest, replaces 2008 rules)
Area PlanDetailed Area Plan (DAP) 2022–2035 – governs FAR, zoning, density
Building CodeBangladesh National Building Code (BNBC) 2020 – structural, fire, safety
Online SystemECPS – Electronic Construction Permitting System (launched 2024)
Portalecps.gov.bd (previously cp.rajuk.gov.bd)
RegulatorRAJUK – Rajdhani Unnayan Kartripakkha

The Two-Stage Mandatory Process

StageNameFormValidityFee
1Planning Permit (LUC)Form-10124 months (+ 12 renewal)Tk 5,000 + 15% VAT
2Construction PermitForm-3013 years (to plinth level)Variable (see p.8)
3*Special Project ApprovalForm-20124 months (non-renewable)Tk 10,000 + 15% VAT
4*Occupancy Certificate5 years (renewable)Variable

* Stage 3 required for large/special projects. Stage 4 required after construction completion.

Fee structure is under revision per draft Dhaka Building Construction Rules 2025. Fees for plan approvals, extensions and land-use clearances are proposed to jump from Tk 1,000 to Tk 5,000, with an additional Tk 5,000/katha for multi-unit residential blocks. Confirm current fees at ecps.gov.bd before payment.

📍2. PHASE 1 – Planning Permit (LUC) | Form-101

The Planning Permit (formerly Land Use Clearance / LUC) is the mandatory first step. It is submitted online through ECPS to RAJUK's Town Planning Department. All documents must be uploaded as original-color JPEG or PNG scans.

2a. Documents Checklist – All Plot Types

Document / ItemNotesStatus
Land Registry (deed of land)
Original color scan, JPEG/PNG
Required
Mutation Certificate
Must be up to date
Required
National ID (NID) or Passport
Owner or authorized representative
Required
CS, RS and MS Khatian
All three khatians required
Required
Duplicate Carbon Receipt (DCR)
From relevant sub-registry office
Required
Updated Land Tax Receipt
Current year's tax clearance
Required
TIN Certificate
Income Tax Identification Number
Required
TAX Return Acknowledgement Slip
Latest year's tax return
Required
Passport-size Photo
1 copy of landowner
Required
LUC Application Form-101
Filled and digitally signed online via ECPS
Required
Application Fee Payment Proof
Bank draft in favor of RAJUK + 15% VAT
Required

Additional Documents – Private / NHA Housing Land

Document / ItemNotesStatus
Possession Letter
Issued by housing authority
If applicable
Provisional and Final Allotment Letter
If applicable
Layout Plan from Housing Office
If applicable
Payment Clearance Slip
If applicable
Sale Permission
If plot was transferred
If applicable
Re-construction Permission
If replacing existing structure
If applicable
Lease Deed with Housing Company
If applicable
Mutation Permission from Housing Authority
If applicable
Time Extension Letter
If allotment has been extended
If applicable

Additional Documents – RAJUK Plots (Uttara, Purbachal, Jheelmil, Banani, Gulshan, Baridhara)

Document / ItemNotesStatus
MIS Clearance from RAJUK
From RAJUK's MIS department
Required
Field Survey Report by RAJUK Surveyor
Must be conducted by authorized RAJUK surveyor
Required
Transfer Declaration Letter
If plot was transferred to current owner
If applicable

Drawings Required for LUC Submission

Document / ItemNotesStatus
Digital Land Survey Report
Scale 1:5,000 or 1:10,000
Required
Site Plan showing land use within 250m radius
Size: 15cm × 20cm
Required
Location Map of Land
Showing plot in context of area
Required
Width of Nearest Road (marked on plan)
Required
RS, CS Map Pantograph Drawing
Official map tracing
Required

Information to Fill in Form-101 (Online)

  • Name of applicant / landowner
  • Present address of applicant
  • Proposed land location (CS/RS Dag No, Mouza, Thana)
  • Area of land in Katha
  • Existing land use of plot
  • Proposed land use
  • Name and width of connecting road
  • Elevation of land with respect to road (Reduced Level)
  • Land use of surrounding plots (North, South, East, West)
  • Ownership history of plot
  • Other land information (if any)

2b. Fees, Timeline & Validity

Application FeeTk 5,000 + 15% VAT (per draft 2025 rules) Bank draft payable to RAJUK at a scheduled bank
Processing TimeOfficial: 30 days from submission (May vary in practice)
Validity24 months from date of approval
RenewalAdditional 12 months via Form-111 (before expiry)
Expired LUCMust re-apply from scratch – previous LUC cannot be reactivated
💡Submit LUC well before your target construction date. Processing can take longer than 30 days. Use the 24-month period to prepare all construction permit drawings.

🏗3. PHASE 2 – Construction Permit | Form-301

After obtaining a valid Planning Permit, apply for the Construction Permit through ECPS using Form-301. This must be submitted within the 24-month LUC validity period. Five drawing sets must be submitted digitally on Ammonia-printed sheets (A0–A2).

3a. Documents Checklist

Document / ItemNotesStatus
Online Application (Form-301)
Submitted via ecps.gov.bd
Required
Valid Planning Permit / LUC Copy
Must be within 24-month validity
Required
Bank Draft – Building Approval Fee
Payable to RAJUK + 15% VAT
Required
All Land Documents (as in LUC section)
Same set as Phase 1
Required
Soil Test Report
Required for buildings on weak soil; check with RAJUK
If applicable
FAR Calculation Sheet
Showing MGC, setbacks, number of storeys, FAR
Required
Ammonia-printed Approval Drawing Sheets (A0–A2)
5 drawing sets – see Section 3b
Required
Indemnity Bond for Piling / Basement Construction
If piling or basement is proposed
If applicable
Floor-wise Number of Apartments
For residential buildings
Required
RAJUK Registration Certificate – Design Architect
With IAB membership number
Required
RAJUK Enlistment Certificate – Structural Engineer
With IEB membership number
Required
RAJUK Enlistment Certificate – Electrical Engineer
With IEB membership number
Required
RAJUK Enlistment Certificate – Plumbing Engineer
With IEB membership number
Required
Fire Expert Certification
Required if Fire Design is submitted
If applicable
Land Surrender Deed to DNCC/DSCC
If road expansion affects the plot boundary
If applicable

3b. Required Drawing Sets (5 sets – all Ammonia printed A0–A2)

① Architectural Design (signed by RAJUK-registered Architect)

Document / ItemNotesStatus
Title block with applicant name, address, mobile, signature
Required
Architect's name, IAB membership no., RAJUK registration no., signature
Required
Structural engineer's details on architectural sheet
Required
LUC approval reference number and date
Required
Occupancy type of proposed building
Required
CS/RS/SA Dag No., Mouza, Thana name
Required
Site Plan (Scale 1:4,000) with boundaries, road width, entry position
Required
Layout Plan (Scale 1:200) – boundary, existing buildings, sewer/water connections
Required
All Floor Plans (Scale 1:100) – room dimensions, door/window sizes, parking
Required
Roof Plan – terrace, chilakatha, lift machine room, OHWT, water disposal
Required
Two Cross-Sections (Scale 1:100) – floor heights, lift, stairs, plinth level
Required
Four Elevations (N/S/E/W) Scale 1:100
Required
Waste collection point location
Required
Generator and sub-station room location
Required

② Structural Design (signed by RAJUK-enlisted Structural Engineer)

Document / ItemNotesStatus
Foundation design and type
Required
Column-beam-slab layout for all floors
Required
Structural analysis for earthquake, wind, dead & live loads (BNBC 2020)
Required
Piling plan with indemnity bond (if applicable)
If applicable
Engineer's IEB membership and RAJUK enlistment details
Required

③ Plumbing Design (signed by RAJUK-enlisted Plumbing Engineer)

Document / ItemNotesStatus
Water supply layout (floor-wise)
Required
Drainage and sewage plan
Required
Underground water reservoir (UGWR) capacity and location
Required
Overhead water tank (OHWT) capacity and location
Required
Septic tank design (if not connected to WASA sewer)
If applicable
Soak well / soakpit design
If applicable

④ Electrical Design (signed by RAJUK-enlisted Electrical Engineer)

Document / ItemNotesStatus
Single-line electrical diagram
Required
Load calculation sheet
Required
Sub-station and generator room location
Required
Lift electrical connections (mandatory >6 floors)
If applicable
Emergency lighting and exit signage plan
If applicable

⑤ Fire Safety Design (signed by certified Fire Expert) — IF REQUIRED

Document / ItemNotesStatus
Fire exit staircase layout (mandatory >10 storeys or >33m height)
If applicable
Fire lift (dedicated) details
If applicable
Sprinkler system layout (high-rise)
If applicable
Hydrant / hose reel system layout
If applicable
Smoke detector / fire alarm layout
If applicable
Fire-rated door and wall locations
If applicable
Water tank dedicated for fire use
If applicable

3c. Professional Qualifications Required

RoleQualificationMembershipExperience
Design ArchitectB.Arch from IAB-accredited universityMember of IABMin 8 years; RAJUK registered under DAP 2022-2035
Structural EngineerBSc Civil Engineering from IEB-accredited universityMember/Fellow of IEBMin 8 years civil; 5 years structural; RAJUK enlisted (SEng/PEng)
Electrical EngineerBSc Electrical EngineeringMember of IEBRAJUK enlisted
Plumbing EngineerBSc Civil / Mechanical EngineeringIEB membershipRAJUK enlisted
Fire ExpertCertified fire safety specialistFSCD recognizedRequired for fire-design submission

3d. Fees, Timeline & Validity

Fees are calculated per floor area. The table below shows the current fee schedule (subject to revision under draft Bidhimala 2025):

Building Type / Floor AreaApproval Fee (approx.)Notes
Residential – small plot, low riseTk 10,000 – 50,000+ 15% VAT
Residential – 5,000 sqmTk 42,500 (current) → Tk 250,000 (proposed)Draft 2025
Large residential / commercial – 30,000 sqmSignificantly higherDraft 2025
Multi-unit block – per katha surchargeTk 5,000/katha (proposed)Draft 2025
Processing TimeOfficial processing: variable; RAJUK targets ~45 days via ECPS
Plan Validity3 years from approval date
Construction RequirementMust reach plinth level within validity period
Failure to Build to PlinthApproved plan becomes invalid – must re-apply
Re-approval Penalty10× the original approval fee + committee-set compensation

Special Conditions

  • Plot must be completely vacant before plan submission
  • Boundary wall must be broken / land surrendered for any proposed road expansion
  • Minimum proposed road width: 20 ft (public land) / 25 ft (housing land) / 12 ft (shared)
  • Minimum plot entry gate width: 18 feet
  • Driveway must be minimum 14 feet wide
  • Lift is mandatory for buildings more than 6 (six) storeys
  • Fire stairs mandatory for buildings >33m in height or >10 storeys (whichever comes first)
  • CAAB height clearance required if plot is near airport or runway

🏢4. PHASE 3 – Special / Large Project Approval | Form-201

Certain projects are classified as 'Special Projects' under Dhaka Mahanagar Imarat Nirman Bidhimala 2025 and require additional approval from RAJUK's Special Project Approval Committee before the construction permit can be issued.

Projects That Qualify as Special Projects

Document / ItemNotesStatus
Residential building with more than 40 flats
Required
Gross Floor Area exceeds 7,500 sqm (per FAR)
Required
Shopping mall with more than 5,000 sqm floor area
Required
Project connecting to a National or Regional Highway
Required
Brick field or hazardous industrial factory
Required
Any project within 250m of a Historical/Heritage Building
Required
Any project within 250m of parks or natural beauty areas
Required
Project within 50m of a hilly area or river bank
Required
Any project within 250m of KPI (Key Point Installation)
Required

Documents Required for Special Project Application

Document / ItemNotesStatus
Land use clearance copy / No-objection copy
Required
Ownership evidence / Land Registry copy
Required
CS, RS, MS Map
Required
Dag No., Mouza and Thana Name
Required
Khatian, Mutation documents
Required
Number of storeys in proposed building
Required
Total cumulative floor area (GFA)
Required
Floor-wise area mentioning use type
Required
Total number of flats (for residential)
Required
FAR Calculation Chart
Required
Required water demand of proposed project
Required
Source of water and supply network diagram
Required
Required electricity load for project
Required
Source of electricity and single-line diagram
Required
Construction start date and phasing plan
Required
Estimated construction completion duration
Required

Special Project Approval Drawings Must Include

Document / ItemNotesStatus
Key plan with site boundary measurements
Required
North directional sign of proposed site
Required
Name and width of connecting road
Required
Holding No., Plot No., and Mouza name
Required
Plot elevation relative to road level
Required
Information on existing buildings inside project boundary
Required
Adjacent building height and distance from plot boundary
Required
Vehicle and pedestrian entry/exit
Required
Drainage system and disposal network
Required
Location of electrical sub-station
Required
Wastewater and sewerage treatment plant (STP) detail
Required
Garbage collection and disposal management plan
Required
Any special building or facility within 250m of proposed land
Required
Processing TimeOfficial: 45 days from application submission
Application FeeTk 10,000 + 15% VAT (bank draft to RAJUK)
Validity24 months from approval date
Renewable?NO – Special Project approval cannot be renewed
Failure to Apply for CPMust re-apply for Special Project approval from scratch

5. Departmental Clearances (>10 Storeys / >33m)

Buildings more than 10 storeys or above 33 metres in height require departmental clearances from 10 separate authorities before RAJUK will issue the Construction Permit. Apply to each in plain paper with location details and related drawings.

#AuthorityPurposeNotes
1DPDC / DESCO / BREB (Power Division)Electrical load requirement clearanceState electricity demand and sub-station details
2DWASA (Water & Sewage Authority)Water consumption and sewerage clearanceSubmit water demand calculation
3Titas Gas & Transmission AuthorityGas connection requirementSubmit gas load calculations
4FSCD (Fire Service & Civil Defence)Fire Safety NOCMandatory for >6 storeys (see Section 6)
5DoE (Dept. of Environment)Environmental clearance / ECCMay require EIA for large projects (see Section 7)
6CAAB (Civil Aviation Authority)Height clearance near airportsRequired near Hazrat Shahjalal International Airport runway corridors
7Roads & Highways / City CorporationRoad connection / access approvalIf project connects to major road
8Telecom Authority (BTRC)Telecom infrastructure clearanceFor large commercial buildings
9District Commissioner / Deputy CommissionerLand-related NOCIf land has any government acquisition status
10Department of Explosives / Petroleum Corp.Hazardous use clearanceFor industrial/chemical uses only
All departmental clearances must be obtained before submitting the Construction Permit application. Delays in any single clearance will delay the entire permit.

🔥6. Fire Safety NOC Requirements

The Fire Service & Civil Defence (FSCD) is the enforcing body for fire-safety compliance and NOCs in Bangladesh. Requirements scale by building height, type, and occupancy. Fire NOC must be obtained from FSCD before RAJUK issues the construction permit for qualifying buildings.

Fire NOC Trigger Thresholds

Document / ItemNotesStatus
Building >6 storeys (high-rise threshold)
Full fire safety system required
Required
Building >10 storeys or >33m height
Fire stairs + fire lift mandatory
Required
Commercial building / shopping mall
Stricter requirements based on occupant load
Required
Assembly occupancy (school, hospital, cinema)
Highest fire safety standards
Required
Industrial / factory / warehouse
Fire licence from FSCD required
Required
Restaurant or food court (any floor)
Especially if above ground floor
Required

Fire Safety Requirements by Category

RequirementApplicable ToStandard
Fire Exit Staircase>10 storeys or >33mBNBC 2020 / FSCD norms
Dedicated Fire Lift>10 storeys or >33mSeparate from passenger lifts
Sprinkler SystemHigh-rise, malls, assemblyFull floor coverage
Fire Hydrant / Hose Reels>6 storeys; commercialEvery floor, accessible
Smoke Detectors / Fire Alarm>6 storeysAll floors, all rooms
Fire-rated Doors & WallsExit corridors & stairwellsMinimum 2-hour rating
Dedicated Water Tank (fire use)>10 storeys; commercialMinimum capacity per FSCD
Emergency Lighting & Exit Signs>6 storeys; assemblyAll exits, stairwells
Portable Fire ExtinguishersAll buildingsPlaced per BNBC schedule
Assembly Point / Refuge Area>10 storeys; assemblyDesignated & marked
The 2024 Bailey Road fire in Dhaka (46 deaths) highlighted critical fire safety gaps. FSCD and RAJUK compliance checks have significantly intensified since. Ensure fire design is prepared by a FSCD-recognized certified fire expert.

🌱7. Environmental Clearance | DoE / ECC

The Department of Environment (DoE) issues Environmental Clearance Certificates (ECC). Large real estate projects may require a full Environmental Impact Assessment (EIA). Over 8,000 ECCs were issued in 2024, a 22% increase from 2023.

Document / ItemNotesStatus
Plot size greater than 10 Katha
May require environmental clearance
If applicable
Project with significant environmental impact
EIA may be required
If applicable
Project in flood-prone zone
Flood zone clearance required
If applicable
Project near wetland or water body
Wetland restriction / special clearance
If applicable
Industrial or factory use
Full EIA mandatory
Required
Project with heavy waste / effluent discharge
STP / ETP mandatory
If applicable
Tree removal required for construction
Tree compensation plan required
If applicable
High noise-generating activities
Noise study may be required
If applicable

Note: Dhaka Imarat Nirman Bidhimala 2025 mandates Sewage Treatment Plants (STP) for larger buildings. Confirm STP requirements with RAJUK/DoE for your project size.

🏠8. Occupancy Certificate

After construction is complete, an Occupancy Certificate (OC) must be obtained from RAJUK before the building can legally be occupied or used. This is mandatory and cannot be skipped.

Document / ItemNotesStatus
Construction Completion Report
Certified by architect and structural engineer
Required
As-Built Architectural Design
Showing actual as-constructed drawings
Required
As-Built Structural Design
Final structural drawings
Required
As-Built Electrical Design
Final electrical drawings
Required
As-Built Plumbing Design
Final plumbing drawings
Required
Building Services Plan
All MEP services as installed
Required
Fire NOC (if applicable)
Updated after construction completion
If applicable
Utility Connection Certificates
WASA, electricity, gas connections confirmed
If applicable
Validity5 years from date of issue
RenewalMust be renewed every 5 years
Expired OCApproved plan becomes invalid; re-approval requires 10× fee
Consequence of No OCBuilding cannot be legally occupied; subject to penalty/demolition

📐9. Key Rules Reference – FAR, Setbacks, Parking & Height

9a. Floor Area Ratio (FAR) – DAP 2022–2035

FAR = Total Cumulative Floor Area ÷ Total Land Area. DAP 2022–2035 sets FAR values by Ward Number, planning area type, and zoning. Planned areas (RAJUK, govt housing) receive higher FAR than unplanned / spontaneous areas.

Area / ZoneFAR RangeNotes
Gulshan, Banani, Baridhara (planned)Up to 6.0–6.5High-density planned zones
Uttara (planned)Up to 5.5–6.0TOD bonus near MRT stations
Dhanmondi, Lalmatia (semi-planned)3.0–5.0Varies by ward
Unplanned spontaneous areas2.5–4.5Depends on road width
TOD Zones (within 500m of MRT)Bonus FAR up to +1.0If 60% open space in block
School / College / University+0.25 bonus FAR
RAJUK/Govt approved housing plot+0.5 bonus FAR
Open-for-all playground/park+0.25 bonus FAR

Use the PlanBD FAR Calculator or visit RAJUK's ward-wise FAR table for your specific plot. FAR values are indexed by Ward Number and planning area designation.

9b. Height Restrictions by Zone – DAP 2022–2035

Zone / AreaMax Height (approx.)Notes
Kuril, Khilkhet, Nikunja (DNCC)6 storeysDAP restriction
Uttara7 storeys (general)Higher in TOD zones
Gulshan, Banani, Baridhara8 storeys (general)Higher in TOD zones
TOD Zone (near MRT station, 500m)Higher permittedBlock open-space condition
Near airport / runwayCAAB clearance requiredApply through RAJUK to CAAB
Fire stairs trigger>10 storeys or >33mWhichever comes first
Lift mandatory>6 storeysCompulsory per rules

9c. Mandatory Setbacks – General Reference

Setbacks depend on road width, plot size, building height, and zone. The FAR Calculation Sheet must show setbacks for all four sides.

Road Width (Front)Min Front SetbackSide SetbacksRear Setback
Up to 20 ft1.5m – 3mPer zone rulesPer zone rules
20 – 40 ft3m – 4.5mPer zone rulesPer zone rules
>40 ft4.5m+Per zone rulesPer zone rules
High-rise (>10 storeys)IncreasedIncreasedIncreased

Precise setback values are defined in the Dhaka Imarat Nirman Bidhimala 2025. Always verify with the FAR calculation sheet from your registered architect.

9d. Parking Requirements – General Reference

Parking requirements are calculated based on building use and gross floor area. The parking plan must show entry, exit, guard post, driveway (min 14 ft wide), disabled bays, visitor bays, and motorcycle bays.

Building TypeCar ParkingMotorcycleNotes
Residential apartment1 per unit (approx.)RequiredVisitor + disabled bays required
Commercial / Office1 per 100–150 sqm GFARequiredHigher in CBDs
Shopping mall1 per 50–100 sqm GFARequiredPer BNBC 2020
Hospital1 per 3 beds + staffRequiredAmbulance bay required
School / CollegePer staff + visitor countRequiredDrop-off zone required
Disabled parkingMin 2% of total or 2 baysPer BNBC 2020

💡10. Common Rejection Reasons & Expert Tips

IssueDescriptionRisk
Expired LUCSubmitting Construction Permit after the 24-month LUC validity has lapsed
HIGH
Incomplete Document SetMissing any one required document causes full rejection
HIGH
Unregistered ProfessionalArchitect or engineer not currently registered with RAJUK
HIGH
FAR ExceedanceProposed GFA exceeds permissible FAR for the ward/zone
HIGH
Setback ViolationBuilding footprint does not respect mandatory setbacks on all sides
HIGH
Missing Soil TestSubmitting without soil test when ground conditions require it
MEDIUM
Inadequate ParkingInsufficient parking bays relative to floor area
MEDIUM
Road Width Non-CompliancePlot entry gate <18 ft or driveway <14 ft
MEDIUM
Incorrect Drawing ScaleDrawings not at specified scales (1:100, 1:200, etc.)
MEDIUM
Non-Color Document ScansDocuments scanned in black-and-white instead of original color
MEDIUM
JPEG/PNG Format ErrorDocuments uploaded in incorrect file format
LOW
Missing Cross-SectionsOnly one section provided instead of two (long + short axis)
LOW

Expert Tips from Experienced Practitioners

💡Engage a RAJUK-registered architect from day one. Unregistered professionals cannot sign approval sheets.
💡Start the LUC application 6–8 months before your planned construction start to absorb delays.
💡Keep the plot completely vacant — RAJUK will reject plans if any structure exists on site at submission.
💡Verify your FAR and ward classification using the latest DAP ward-wise table before commissioning drawings.
💡Use ECPS's online tracking to monitor your application status in real time.
💡For plots near MRT stations, check if your area qualifies as a TOD zone — you may get bonus FAR.
💡Confirm current fee amounts at ecps.gov.bd as the 2025 fee revision is pending gazette notification.
💡Ensure all four elevations (N/S/E/W) and two cross-sections are included — missing these is a common cause of rejection.
💡If your building requires fire stairs, engage a fire consultant early — the fire staircase affects the entire floor plan layout.

📚11. Regulation Timeline & Amendment History

Understanding the evolution of regulations helps identify which rules apply to your project and whether any recent amendment affects your submission.

YearRegulation / EventKey Impact
1952Building Construction Act (Act No 1107/1953)Primary legal authority for all building approvals in Bangladesh
1993BNBC – Bangladesh National Building Code (first draft)First national building code; became legally binding in 2006
2008Dhaka Mahanagar Imarat Nirman Bidhimala 2008Primary building rules for Dhaka; governed until 2025
2010RAJUK restructuringExpanded jurisdiction; introduced systematic plan approval
2020BNBC 2020 (updated)Stricter structural, fire, and environmental standards
2021Imarat Nirman Unnayan Poriborton Bidhimala 2021Amendment to 2008 rules; introduced new zoning provisions
2022DAP 2022–2035 (Detailed Area Plan)New zoning, FAR limits, height restrictions, TOD zones for Dhaka
2023SRO 271/2023Amendment to DAP; revised FAR and density rules
2024ECPS Launched (ecps.gov.bd)Full digitization of construction permit process
Dec 2025DAP Update – 14 December 2025Latest update to DAP rules; current benchmark
2025Dhaka Imarat Nirman Bidhimala 2025NEW – replaces 2008 rules; STP mandates, revised fees, updated FAR
2025–26Draft Building Construction Rules 2025Proposed fee hikes (5×), new categories; pending gazette notification
2026+Future AmendmentsMonitor rajuk.gov.bd and ecps.gov.bd for updates

Official Reference Links

RAJUK Officialrajuk.gov.bd
ECPS Portal (Online Applications)ecps.gov.bd
RAJUK Notices & Circularsrajuk.gov.bd/pages/notices
DAP 2022–2035 DownloadAvailable at rajuk.gov.bd
BNBC 2020 DownloadAvailable at hpw.gov.bd
Fire Service & Civil Defencefireservice.gov.bd
DoE Environmental Clearancedoe.gov.bd
DWASA (Water Authority)dwasa.org.bd
Disclaimer: This document is produced by PlanBD as a reference guide based on publicly available information and research as of June 2026. Regulations are subject to change. Always verify requirements directly with RAJUK (ecps.gov.bd / rajuk.gov.bd) before submitting any application. PlanBD is not responsible for regulatory changes post-publication. For legal advice, consult a RAJUK-registered architect or legal professional.